Administratief Akkoord tussen het Koninkrijk der Nederlanden en de Volksrepubliek Bangladesh inzake het project 'Char Development and Settlement Project – Bridging (Additional Financing)'
- BWB-id
- BWBV0006918
- Type
- verdrag
- Ministerie
- Buitenlandse Zaken
- Geldigheid
- Geldend vanaf 2023-09-03
Wetstechnische informatie / identifiers
- BWB-id
- BWBV0006918
- ELI
- /eli/nl/verdrag/2021/bwbv0006918
- ELI (gepinde datum)
- /eli/nl/verdrag/2021/bwbv0006918/2023-09-03
- JCI 1.0 (vindplaats)
- wetten.overheid.nl/1.0:c:BWBV0006918&g=2023-09-03
- JCI 1.3 (citatie)
- jci1.3:c:BWBV0006918&z=2026-06-06&g=2023-09-03
- Op wetten.overheid.nl
- https://wetten.overheid.nl/BWBV0006918/2023-09-03
Absolute ELI: /eli/nl/verdrag/2021/bwbv0006918
Artikel I — Article I (The Project)#
Article I (The Project) 1 The two Parties shall jointly carry out a Project, entitled “Char Development and Settlement Project – Bridging (Additional Financing)”, hereinafter referred to as “the Project”. 2 The aim of the Project is the preparation of future Char Development and Settlement Programmes, the development of permanent institutional framework for such programmes and the planning, execution, supervision and monitoring of activities in the field of water management, rural infrastructure, institutional development, land-settlement, agricultural value chains, social development and gender-inclusivity. 3 The aforesaid co-operation between the two Parties is planned to last from 1 July 2019 to 30 June 2024, or shall expire on the date on which the Project has been completed in conformity with the provisions of the Administrative Arrangement and of the DPPs of the Project, whichever date is the later. 2023 110 25-09-2023 2023 110 25-09-2023 03-09-2023 01-07-2022
Artikel II — Article II (The contribution by the Netherlands Party)#
Article II (The contribution by the Netherlands Party) The Netherlands Party shall make an additional contribution of € 2.296.615 (top-up to accommodate the extension) on top of € 5.000.000 (the original TA budget, as concluded on 29 April 2021 and 23 May 2021), € 7.296.615 in total (seven million two hundred and ninetysix thousand six hundred and fifteen euros) in the form of grant to the Project in the following manner: The Netherlands Party's contribution will become available on the condition that: – € 2.296.615 (top-up to accommodate the extension) for Technical Assistance, through direct contracting by the Netherlands Party. – The Bangladesh Party shall have approved the Development Project Proformas (DPPs) of all five participating departments (BWDB, LGED, DPHE, Forestry Department, Land); and – The Bangladesh Water Development Board shall have appointed the Project Coordination Director. 2023 110 25-09-2023 2023 110 25-09-2023 03-09-2023 01-07-2022
Artikel III — Article III (The contribution by the Bangladesh Party)#
Article III (The contribution by the Bangladesh Party) The Bangladesh Party shall make the equivalent of US$ 24.880.000 available to the Project. The Bangladesh Party will also obtain a loan of US$ 20.600.000 from the International Fund for Agricultural Development as additional financing for the implementation of the project. 2023 110 25-09-2023 2023 110 25-09-2023 03-09-2023 01-07-2022
Artikel IV — Article IV (The Executive Authorities)#
Article IV (The Executive Authorities) 1 The Netherlands Party shall appoint the Embassy of the Kingdom of the Netherlands as the Netherlands Executive Authority in charge of the Project. The Netherlands Executive Authority shall be represented, as far as the daily operations of the Project are concerned, by the Leader of the Technical Assistance Team (being the Team Leader or in his absence the Deputy Team Leader, hereinafter referred to as “TL/DTL”). 2 The Bangladesh Party shall appoint the Bangladesh Water Development Board, as the Bangladesh Executive Authority in charge of the Project. The Bangladesh Executive Authority shall be represented, as far as the daily operations of the Project are concerned, by the Project Coordination Director. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel V — Article V (Delegation)#
Article V (Delegation) Each of the Executive Authorities shall be entitled to delegate under its own responsibility, partly or entirely, its duties in connection with the Project to other authorities or organisations. In doing so, the Executive Authorities shall inform each other in writing of any such delegation and of the extent of the delegation. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel VI — Article VI (The TL/DTL)#
Article VI (The TL/DTL) 1 The TL/DTL shall be responsible to the Netherlands Executive Authority for the proper implementation of the Netherlands contribution. 2 The TL/DTL shall act in close consultation with the Bangladesh Executive Authority and shall respect the operational instructions given by the said Authority. 3 The Bangladesh Executive Authority shall provide the TL/DTL with any information that may be considered necessary for the execution of the Project. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel VII — Article VII Schedule of Operations (The)#
Article VII Schedule of Operations (The) 1 Schedule of Operations The Executive Authorities shall establish in common agreement aindicating in detail: – the contribution of either Party; – the number and duties of the staff appointed by each Party; – their job-descriptions; – the duration of their assignment; – a time-table; – a description of the equipment and materials to be made available. 2 Schedule of Operations Theshall form an integral part of this Administrative Arrangement. 3 Schedule of Operations Themay be amended in common agreement by the Executive Authorities. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel VIII — Article VIII (Status of the Netherlands Staff)#
Article VIII (Status of the Netherlands Staff) Articles II III of the Agreement The personnel supplied by the Netherlands Party shall enjoy the privileges and immunities, mentioned in theand. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel IX — Article IX (Equipment and Materials)#
Article IX (Equipment and Materials) 1 Articles IV V of the Agreement The provisions ofandshall be applicable to the import and export of the equipment and materials provided by the Netherlands Party as well as to the status of the said equipment and materials. 2 Without prejudice to the payment by the Bangladesh Party or the Bangladesh recipient agency of the customs duties and taxes on the equipment and materials supplied by the Netherlands Party, those customs duties and taxes are due upon the transfer of the equipment and materials to the Bangladesh Party or Bangladesh recipient agency. The Netherlands Party is in no way under an obligation to pay the customs duties or taxes. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel X — Article X (Reporting)#
Article X (Reporting) The TL/DTL and the Project Director shall submit to both Executive Authorities a semi-annual report (both narrative and financial) in English. The first annual report on the progress made in the execution of the Project and on the expenditure incurred by both Parties will cover the period from start until 31 December 2019. The information on the Technical Assistance (TA) budget expenditure will be shared with the Bangladesh Party. On completion of the Project, the TL/DTL and the Project Director shall submit to all parties involved a final report in English on all aspects of the work done in connection with the Project. All reports including the final report of the Project will be provided to the Bangladesh Party also. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel XI — Article XI (Evaluation)#
Article XI (Evaluation) The Executive Authorities shall have the Project reviewed through a joint Mid-Term Review mission; the timing and the Terms of Reference (ToR) of this mission will be determined by both Executive Authorities. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel XII — Article XII (Settlement of disputes)#
Article XII (Settlement of disputes) Any dispute concerning the interpretation or implementation of this Administrative Arrangement, which cannot be settled in consultation between both Parties shall be referred to the respective Governments and shall be settled in a way to be decided upon by the latter. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019
Artikel XIII — Article XIII (Entry into force and duration)#
Article XIII (Entry into force and duration) Article I, paragraph 3 This Administrative Arrangement shall enter into force on the day of signature by both Parties with retrospective effect to 1 July 2019, and shall expire at the end of the period mentioned in, of this Administrative Arrangement or on the date on which the Project has been completed in conformity with the provisions of this Administrative Arrangement and of the DPPs of the Project, whichever date is the later. 2021 106 20-07-2021 2021 106 20-07-2021 23-05-2021 01-07-2019